Community Announcement: Directional Flushing Plan for MUD 401

June 10, 2024 12:34 pm

Attention Residents,

As authorized by the Board, we will commence the directional flushing plan on Monday, June 10th, and it will conclude on Monday, June 17th. The Maintenance of Operations (MoC) team will be working Monday through Thursday (June 10th to June 13th) and will complete the plan the following Monday (June 17th). No weekend work will be performed.

All flushing activities will take place between 9:00 AM and 4:00 PM to ensure the system is operating optimally during peak hours. Rest assured, customers will not experience any service interruptions while flushing is underway.

We appreciate your cooperation and understanding during this essential maintenance period.

Thank you,

MUD 401 Board

Dark ModeLight Mode